Irrigation Department, Government of Balochistan
Balochistan – Pakistan
Pak Rs. 27,457.73 Million
Jan-2013
Project Director, Construction of 100 dams, Balochistan
6,610 Man-Months
Pak Rs. 789.28 Million
Jun-2025
(Contractually)
Project is aimed at managing floodwaters by constructing 100 small dams in all 35 districts across Balochistan. The project is funded by Federal Government of Pakistan and it is divided into 05 packages (20dams/Package). More than 60 have already been constructed under first 3 packages whereas package-4, is presently under construction. The basic types of dams proposed comprise of concrete gravity dams, modified homogeneous and zoned earth embankment sections with maximum height varying from 40ft to 110ft. (10 m to 35 m. The 60 constructed dams have so far provided a storage capacity of more than 300,000AF and command area more than 110000acres within a period of 15 years.